My build time line
15th March - Paid deposit for house plans
24th April - Received house plans
18th May - Colour Selection
20th May - Plans went to council
22nd May - Septic plans went to council
26th August - House plans finally got approved at council
16th October - Septic system finally approved
19th November - Signed building contracts
15th December - Received letter to commence
23rd December - Signed final plans and Price
29th December - Received a 25 day extension for the Christmas shutdown.
23rd January - Cut & fill started
24th January - Slab framing started
27th January - Toilet Delivered and fences put up
30th January - Peering done and waffle pods, rio and gravel delivered